In celebration of Spring showers, SES reflects on our recent Site Storm Drainage Improvement project done for a local processing facility.

This project posed significant challenges due to heavy rainfall causing standing water at the site.

PROJECT HIGHLIGHTS
• Excavation of a ½ acre stormwater retention pond.
• Relocated over 5,000 CY of soil.
• Installed a concrete sediment chamber and a concrete pump chamber.
• Installed an HDPE liner in pond.
• Installed over 300 LF of 12 HDPE drainage pipe with 7 storm inlets.
• Installed an HDPE liner in the drainage swale.
• Installed six check dams into the drainage swale