Project Spotlight: Clean Demo of 8th Floor Parking Garage

Sessler Environmental Services was contracted by a Veterans Affairs Medical Center to repair the parking garage prior to an installation of a snowmelt system.
PROJECT HIGHLIGHTS:
• Breakup and load out 50,000 square feet of 4-inch concrete deck overlay
• Accelerated schedule of 20 days
• Due to the structure of the parking garage, heavy equipment was unable to be used. Therefore, SES used multiple jackhammers and shovels for the removal
• Safe and proper disposal and recycling of debris materials