Former Manufactured Gas Plant (MGP), Newark, New York

Project Location: Newark, New York

Project Highlights:

  • Utilization of a slide rail shoring system on 12 cells to achieve an excavation depth of up to 21’.
  • Remediated nearly 4,500 tons of contaminated soil.
  • Imported 133 CY of flowable fill into excavated cells.
  • Set up and maintained a water treatment system, which treated 70,000+ gallons of impacted water.

Watch the video below for more information about this project!