Former Paint Manufacturing Facility, Tonawanda, New York

Project Location: Tonanwanda, New York

Project Highlights:

  • Performed environmental remediation at a former paint manufacturing facility.
  • Excavated over 2,500 tons of contaminated soil and removed approximately 90 solidified paint drums.
  • Solidified paint was properly disposed of at an approved disposal facility.
  • Treated, tested, and properly disposed of 6,500 gallons of water into the sewer system under permit.